Baltimore's citywide data center moratorium, bill 26-0158, was signed by the Mayor on June 16, 2026, its own record shows; two other data center bills show no vote in the records read.
City Council records show three separate data center bills and one informational hearing. The moratorium bill, 26-0158, makes a data center capable of using 10 megawatts or more a prohibited use citywide. Its own history records committee approval with amendment on May 7, 2026, council approval on May 11, 2026, and the Mayor's signature on June 16, 2026; its status reads Enacted, number 26-128. The signed copy says it takes effect 30 days after it is enacted, and the council-approved text says it lasts 1 year from that effective date. FileDigr does not print a computed start or end date. A second bill, 26-0217, would lower the line to data centers capable of using 5 megawatts or more; it is listed among bills introduced on July 13, 2026, and no hearing on it appears. A third bill, 26-0174, would make data centers a conditional use that needs a Health Equity Assessment; its committee hearing was recessed on September 24, 2026. The Public Health & Environment Committee informational hearing, 26-0050R, was recessed on May 6, 2026 and again on September 23, 2026. The records name no company and no site.
Limit: Only 1 of 5 kinds of record was checked: agendas, agenda item lists and minutes of these bodies only, for meetings from March 12, 2026 to November 7, 2026: Baltimore City Council, Committee of the Whole, Land Use & Transportation Committee, Public Health & Environment Committee, Housing & Economic Development Committee, and Board of Estimates. No City Council minutes were among the stored files, and the Board of Estimates files held no readable agenda text. Also read: the record, history, signed copy and third reader of the moratorium bill, 26-0158. Not read: other bills' attached text, agency reports and hearing packets, other committees, building and zoning permits, land records and utility filings, so their silence tells you nothing.
Where it stands
The moratorium bill, 26-0158, is enacted (Ordinance 26-128): approved by the council May 11, 2026 and signed by the Mayor June 16, 2026. It takes effect 30 days after enactment and lasts 1 year. Bill 26-0217 (5 megawatts) is listed as introduced on July 13, 2026, with no hearing in the records read. The hearing on bill 26-0174 was recessed on September 24, 2026, and the informational hearing 26-0050R on September 23, 2026.
Next documented step
The records give no next date for any data center item. Both recessed hearings show no date to resume, and none of the agendas FileDigr read for meetings up to November 5, 2026 lists a data center bill. Source: Baltimore City Council meeting records on the public Legistar site, read October 8, 2026. Agendas are added before meetings, and dates can change.
More about this findingShowHide
What kind of finding
Rules and a pause. This finding is about how the city regulates data centers. It is not a proposed project and not a decision on one. The records read name no company and no site.
Documented stage
The records show the moratorium bill's committee vote, council approval and the Mayor's signature, and its signed text. They show no full council vote count and no vote on the other two bills.
Place
Baltimore City, Baltimore City, Maryland. The records come from the Baltimore City Council and its committees. FileDigr treats Baltimore City as one area. Baltimore County is a separate government and was not read.
Last successful check
Meeting records: October 8, 2026.
The evidence
Select a conclusion to see the record it came from.
Baltimore City: data center moratorium and zoning bills
The agenda and minutes text names no company and no site. Records read: bills 26-0158, 26-0174 and 26-0217 and resolution 26-0050R, as they appear in City Council and committee agendas, agenda item lists and minutes, plus the record, history, signed copy and third reader of bill 26-0158.
What is still open before the council
Two bills and an informational hearing, each a separate council file. None shows a vote in the records FileDigr read.
What the record says
Selected passage
Data Centers Over 5 Megawatts - Moratorium FOR the purpose of establishing a data center capable of using 5 megawatts or more of electricity as a prohibited use Citywide; and defining certain terms.1 26-0217
1Why this matters: The purpose line gives the 5 megawatt line and says prohibited use Citywide.
In plain words: A megawatt is a unit of electric power. The record gives the number and no comparison. A prohibited use is one the zoning rules do not allow.
Baltimore City Council. Meeting date July 13, 2026.
A second, narrower ban is proposed: data centers that can use 5 megawatts of electricity or more would not be allowed anywhere in the city. It is a separate bill from the moratorium bill 26-0158.
What it does not establish
That the bill has had a hearing or a vote. The agenda lists it for introduction and names a committee. None of the agendas FileDigr read, which run to November 5, 2026, lists it again. Unlike the purpose line of 26-0158, this one does not mention any provision ending; FileDigr did not read the bill text.
Next step, what changed, and document detailsShowHide
Next documented step
No hearing date appears in the agendas FileDigr read, which run to November 5, 2026.
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Bill 26-0217: Data Centers Over 5 Megawatts - Moratorium, Agenda, page 5, Bills Introduced
Office or outlet
Baltimore City Council
Meeting date
July 13, 2026
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
The agenda lists this bill under the heading "Bills Introduced" and names the Land Use and Transportation Committee after it.
What the record says
Selected passage
26-0174 Zoning - Conditional Use - Health Equity Assessment - Data Centers FOR the purpose of establishing data centers as a conditional use by ordinance; establishing the Health Equity Assessment as an additional requirement for certain conditional uses; requiring a Health Equity Assessment for a data center conditional use; and defining certain terms.2
2Why this matters: The purpose line names the conditional use and the Health Equity Assessment.
In plain words: A conditional use is one that needs special approval first. A recessed hearing is paused, not closed.
Baltimore City Council, Land Use & Transportation Committee. Meeting date September 24, 2026.
This bill takes a different approach from a ban: a data center would be a conditional use, approved by ordinance, and would need a Health Equity Assessment. The committee opened its hearing and paused it.
What it does not establish
That the bill has passed or had a committee vote. The minutes record the hearing as recessed and give no date to resume it. FileDigr did not read the bill text, so it does not know what the assessment must cover or which zones the bill reaches. A conditional use rule does not mean any data center has applied.
Next step, what changed, and document detailsShowHide
Next documented step
The minutes give no date to resume the hearing, and none of the agendas FileDigr read, which run to November 5, 2026, lists it.
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Bill 26-0174: Zoning - Conditional Use - Health Equity Assessment - Data Centers, Minutes, page 3
Office or outlet
Baltimore City Council, Land Use & Transportation Committee
Meeting date
September 24, 2026
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
After the sponsors' names, the minutes record for this item: "This Hearing Was Recessed". The bill was first listed on the City Council agenda of April 27, 2026, among bills introduced.
What the record says
Selected passage
FOR the purpose of inviting the Office of the People's Counsel and the Public Service Commission and requiring the Department of Planning, Law Department, Department of Finance, Health Department, and the Department of Public Works to appear before the City Council to discuss: (1) the impact a data center may have on Baltimore City's infrastructure, environment, and its community as a whole; (2) best practices for data center zoning, use standards, and other development standards; and (3) which techniques and technologies are available to limit the public health and environmental impact of these increasingly common facilities. Hearing was recessed.3
3Why this matters: The minutes record the hearing as recessed, right after its stated purpose.
In plain words: An informational hearing is a fact-finding session. It does not pass or reject anything.
Baltimore City Council, Public Health & Environment Committee. Meeting date September 23, 2026.
The council's health committee is holding a fact-finding hearing on what data centers could mean for the city's infrastructure, environment and community, with the People's Counsel, the Public Service Commission and city departments called to appear. It met on May 6 and on September 23, 2026, and both times the hearing was recessed rather than closed.
What it does not establish
Any decision. An informational hearing gathers information; it does not pass or reject a rule. FileDigr did not read the presentations, testimony or department reports attached to the hearing, only their names. The minutes give no date to resume.
Next step, what changed, and document detailsShowHide
Next documented step
The minutes give no date to resume the hearing, and none of the agendas FileDigr read, which run to November 5, 2026, lists it.
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Resolution 26-0050R: Informational Hearing - Data Centers - Community Impact and Use Standards, Minutes, page 1
Office or outlet
Baltimore City Council, Public Health & Environment Committee
Meeting date
September 23, 2026
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
The committee's minutes for May 6, 2026 record the same hearing as "Hearing called to recess." The resolution was first listed on the City Council agenda of March 23, 2026, among resolutions introduced.
The moratorium, bill 26-0158 (Ordinance 26-128)
A separate bill from the items above. Its own record shows it introduced, recommended by committee with amendment, approved by the council on May 11, 2026 and signed by the Mayor on June 16, 2026.
What the record says
Selected passage
2026-05-11 | Baltimore City Council | Approved and Sent to the Mayor | This Ordinance was Approved and Sent to the Mayor to the Mayor. 2026-06-16 | Mayor | Signed by Mayor | This Ordinance was Signed by Mayor to the Baltimore City Council.4
4Why this matters: The history line records the Mayor's signature and its date.
In plain words: Council approval sends a bill to the Mayor; the Mayor's signature makes it law.
Baltimore City Council. File created March 23, 2026; final action June 16, 2026.
The moratorium bill became law. The council approved it on May 11, 2026 and the Mayor signed it on June 16, 2026. The record's status reads Enacted, with enactment number 26-128.
What it does not establish
The full council's vote count; the history records the approval without a tally, and no City Council minutes were among the files read. May 11 is the council's approval, not the signing.
Next step, what changed, and document detailsShowHide
Next documented step
The ordinance takes effect 30 days after it is enacted (see the signed copy).
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Bill 26-0158, Data Centers - Moratorium: legislative history, History steps for May 11 and June 16, 2026
Office or outlet
Baltimore City Council
File created
March 23, 2026
Final action
June 16, 2026
Enactment number
26-128
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
The bill's record on the council's Legistar site reads status "Enacted" and enactment number "26-128". These lines come from the record's history, read October 8, 2026.
What the record says
Selected passage
(2) THAT IS CAPABLE OF USING 10 MEGAWATTS OR MORE OF ELECTRICITY.5
5Why this matters: This line sets the size a facility must reach to fall under the moratorium.
In plain words: A megawatt is a measure of electric power.
Baltimore City Council. File created March 23, 2026; final action June 16, 2026.
The citywide moratorium reaches data centers that can use 10 megawatts or more. Smaller facilities are outside this definition.
What it does not establish
That any data center of that size is proposed in Baltimore. The ordinance names no company and no site. The separate bill 26-0217, which would lower the line to 5 megawatts, is a proposal, not law.
Next step, what changed, and document detailsShowHide
Next documented step
Bill 26-0217 (5 megawatts) shows no hearing in the records read.
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Council Bill 26-0158 (Ordinance 26-128), signed copy, Signed copy attached to the record, definition of data center
Office or outlet
Baltimore City Council
File created
March 23, 2026
Final action
June 16, 2026
Enactment number
26-128
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
The signed copy is a scan, read by picture.
What the record says
Selected passage
SECTION 5. AND BE IT FURTHER ORDAINED, That this Ordinance takes effect 30 days after it6
6Why this matters: Section 5 sets when the moratorium starts.
In plain words: Enacted means it became law.
Baltimore City Council. File created March 23, 2026; final action June 16, 2026.
The moratorium lasts one year from the day it takes effect, then ends without further council action.
What it does not establish
An end date written out. FileDigr does not compute one. The year runs from the effective date, not from the May 11, 2026 council approval.
Next step, what changed, and document detailsShowHide
Next documented step
The ordinance also orders a data center impact study, with a report due no later than 9 months after enactment.
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Council Bill 26-0158, third reader, Third reader attached to the record, Section 4
Office or outlet
Baltimore City Council
File created
March 23, 2026
Final action
June 16, 2026
Enactment number
26-128
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
The signed copy repeats this Section 4, but its scan reads the number as a stray mark, so FileDigr quotes the same line from the third reader text the council approved, attached to the same record.
What the record says
Selected passage
Bills Introduced Data Centers - Moratorium FOR the purpose of establishing a data center as a prohibited use Citywide; defining certain terms; making conforming changes; providing for a special effective date; and providing for the termination of certain provisions of this Ordinance.8 26-0158
8Why this matters: The purpose line says prohibited use Citywide and mentions the termination of certain provisions.
In plain words: A moratorium is a temporary pause. This bill does it by making data centers a prohibited use.
Baltimore City Council. Meeting date March 23, 2026.
The committee that handles land use backed the moratorium bill with changes and sent it on to the full council.
What it does not establish
What the amendments were, or the full council's vote. The minutes do not describe the amendments, and the vote was 5 yes with one member out of the chamber and one excused, not a full committee.
Next step, what changed, and document detailsShowHide
Next documented step
The City Council agenda for May 11, 2026 lists the committee report and lists the bill under Third Reader. That is an agenda listing, not a vote.
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Bill 26-0158: Data Centers - Moratorium, committee hearing, Minutes, page 1
Office or outlet
Baltimore City Council, Land Use & Transportation Committee
Meeting date
May 7, 2026
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
The minutes list 5 members voting yes, 1 out of the chamber, and 1 excused from the meeting. They list no votes against.
What the record says
Selected passage
Approval of the Journal June 15, 2026 Bills Signed by the Mayor June 16, 202610
10Why this matters: The heading names the Mayor's signature and opens the list that includes 26-0158.
In plain words: An agenda is the council's list of business for a meeting. This section lists bills reported as signed.
Baltimore City Council. Meeting date June 22, 2026.
The council's own agenda places the moratorium bill among bills signed by the Mayor, under the date June 16, 2026.
What it does not establish
On its own, an agenda heading is a listing, not the signature itself. The bill's own history (above) records the Mayor's signature on June 16, 2026.
Next step, what changed, and document detailsShowHide
Next documented step
The records read show no later council step for this bill.
What changed
First read by FileDigr on October 8, 2026, so there is no earlier check to compare against.
Document
Baltimore City Council agenda: Bills Signed by the Mayor, Agenda, page 2 (heading) and page 6 (bill 26-0158)
Office or outlet
Baltimore City Council
Meeting date
June 22, 2026
Retrieved by FileDigr
October 8, 2026
Last successful check
October 8, 2026
The quoted heading opens a list that runs to the heading "Bills Introduced". Bill 26-0158, "Data Centers - Moratorium", appears in that list on page 6, with the same title and purpose as on March 23, 2026.
What cuts the other way
The records are about city rules and a pause. The agenda and minutes text names no company, no site and no proposed data center, and does not say why the bills were filed.
The moratorium takes effect 30 days after it is enacted and lasts 1 year from then. The record gives the signing date, June 16, 2026; FileDigr does not print a computed start or end date.
No City Council minutes were among the files read, so the full council's vote count on the moratorium bill does not appear. The bill's history records the approval without a count.
Bills 26-0217 and 26-0174 show no committee or council vote in the records read. They may change or not pass.
The two hearings were recessed, not closed, and the records give no date to resume them.
The Board of Estimates files held no readable agenda text, and one City Council agenda item list (June 1, 2026) was empty, so anything on those is missed.
The attached bill text, hearing packets, permits, land records and utility filings were not checked, so what they might show is unknown.
More detail
Dates in orderShowHide
These entries are not a required sequence. Each one links to its record.
March 23, 2026The City Council agenda lists bill 26-0158, Data Centers - Moratorium, among Bills Introduced and names the Land Use and Transportation Committee (meeting agenda). Original record (opens in a new tab)
March 23, 2026The same agenda lists resolution 26-0050R, an informational hearing on data centers, among Resolutions Introduced and names the Public Health and Environment Committee (meeting agenda). Original record (opens in a new tab)
April 27, 2026The City Council agenda lists bill 26-0174, Zoning - Conditional Use - Health Equity Assessment - Data Centers, among Bills Introduced and names the Land Use and Transportation Committee (meeting agenda). Original record (opens in a new tab)
May 6, 2026The Public Health & Environment Committee minutes record that the hearing on resolution 26-0050R was called to recess (meeting minutes). Original record (opens in a new tab)
May 7, 2026The Land Use & Transportation Committee voted to recommend bill 26-0158 favorably with amendment to the Baltimore City Council, with 5 members voting yes (meeting minutes). Original record (opens in a new tab)
May 11, 2026The City Council agenda lists bill 26-0158 with the committee report Recommend Favorable With Amendments, and lists it again under Third Reader (meeting agenda). Original record (opens in a new tab)
May 11, 2026The moratorium bill's history records that the Baltimore City Council approved it and sent it to the Mayor (bill history). Original record (opens in a new tab)
June 22, 2026The City Council agenda lists bill 26-0158 under Bills Signed by the Mayor, June 16, 2026 (meeting agenda). Original record (opens in a new tab)
July 13, 2026The City Council agenda lists bill 26-0217, Data Centers Over 5 Megawatts - Moratorium, among Bills Introduced and names the Land Use and Transportation Committee (meeting agenda). Original record (opens in a new tab)
September 23, 2026The Public Health & Environment Committee minutes record that the hearing on resolution 26-0050R was recessed (meeting minutes). Original record (opens in a new tab)
September 24, 2026The Land Use & Transportation Committee minutes record that the hearing on bill 26-0174 was recessed (meeting minutes). Original record (opens in a new tab)
Where we looked: 1 checked, 4 not checkedShowHide
Not checked means no result either way.
Baltimore City Council meetings (public Legistar site)Checked. Last successful check October 8, 2026 (today). Reaches back: Meetings from March 12, 2026 to November 7, 2026 (the stored meeting records run from March 12, 2026 to November 5, 2026): agendas, agenda item lists and minutes of the Baltimore City Council, Committee of the Whole, Land Use & Transportation Committee, Public Health & Environment Committee, Housing & Economic Development Committee, and Board of Estimates.Known gap: No City Council minutes were in the store, so the full council's votes were not read. The Board of Estimates files held no readable agenda text, and the City Council agenda item list for June 1, 2026 was empty. The files attached to each bill were read by name only. Other committees and boards on the same site were not read.
Bill text, agency reports and hearing packets attached to council filesNot checked. Not read yet. FileDigr read only their names in the agenda item lists. Exception: the record, history, signed copy and third reader of the moratorium bill, 26-0158, were read on October 8, 2026.
Building and zoning permitsNot checked. No tested way to read this system yet.
Land records (deeds and parcel transfers)Not checked. No tested way to read this system yet.
Utility filings for the areaNot checked. Not supported yet.
Real records - read by FileDigr from the public meeting records of Baltimore City on October 8, 2026. FileDigr is not a government service. Printed from: Baltimore, Maryland: what the records show.